Replies: 3 comments 2 replies
-
|
This is as far as I have got with a list. Note they are NOT in order of preference, and for several I do not yet have viable solutions..
|
Beta Was this translation helpful? Give feedback.
-
|
Right, so I've had a go at prioritising @ahawkes's tasks above. I've thrown in a few small ones from the backlog, but there are plenty more small things that I haven't included for now in the interests of space. I'll make sure to include the important ones in the proposal. Once we're happy with the priorities, we'll need to whittle it down to the tasks that we actually have time for when we write the proposal. Are you broadly happy with the below @ahawkes?
|
Beta Was this translation helpful? Give feedback.
-
|
Looks good. Maybe just move flexible assets to be above trade? |
Beta Was this translation helpful? Give feedback.
Uh oh!
There was an error while loading. Please reload this page.
Uh oh!
There was an error while loading. Please reload this page.
-
MUSE XII engagement
This page is for discussing the plans for the current MUSE2 engagement. For now, I'll just put some discussion points here for our meeting on Weds. If anyone has anything else to add, feel free to leave a comment.
The main thing to be decided is what features should be tackled next and in what order.
Summary of previous engagement
Most of the planned tasks for this engagement were achieved, though some features planned for the second milestone were not. Other unplanned work was carried out (e.g. the revamp of the dispatch optimisation and many small features). Many of the features planned for the second milestone ended up being in the first release (v2.0.0) instead. See here for full list of issues closed for first release.
The two stretch goals for the second milestone were #509 and #523. There wasn't time to start on these, though these could potentially be worked on for this engagement. We will need guidance on how to implement them though.
Plans for current engagement
Now that we have a first release with a basic version of MUSE2 working, we should be making releases much more regularly going forward. I suggest we aim for a new release every one or two months while we're actively working on MUSE2, which should mean we get at least two more releases out during this engagement. I don't think we need to decide what goes in each release at this point though; let's just prioritise first.
@tsmbland and @martinstringer suggested a list of features we may want to consider next, so I'll include these here as I think it's a good starting point for discussion:
agent_cost_limits.csv-- done?)Some other big features to discuss:
We should also discuss features/fixes that are less exciting that need to be done anyway, e.g.:
demandfile #850Input/validation:
Other tooling?
Other questions
Beta Was this translation helpful? Give feedback.
All reactions